Construction on the Shuswap North Okanagan Rail Trail has been progressing this winter thanks to mild conditions and steady work by Yucwmenlucwu (Caretakers of the Land) LLP, a subsidiary of the Splatsin Development Corporation.
According to the Columbia Shuswap Regional District, crews have raised a section of rail bed south of Rosemond Lake to reduce flood risk. They also graded and surfaced the corridor between km 15 and 32 north of Enderby and worked with nearby farms to accommodate existing vehicle and waterline crossings.
Despite the progress, public access remains prohibited as the area is still an active construction zone.
“The project team is currently finalizing road crossing permits with the provincial Ministry of Transportation and Infrastructure. Once approved, crossings will be installed,” said a statement from Splatsin.
Work is also underway to repair and deck three rail bridges along the corridor using reclaimed wood from the former Baxter Bridge at Ashton Creek.
“Major erosion repair work is planned for the Mara Lake section of the trail in February, pending final provincial permits,” the statement continued. “If approvals are delayed, this work may need to be postponed until the next low-water window in August.”
Project updates will be provided as construction progresses. For now, sections of the trail along Mara Lake, through Enderby and Splatsin, and into Armstrong remain open to the public.